Task | Start | Finish | Resource | Description | Baseline | Actual |
1.1 SD feasability study |
2009-02-20 | 2009-02-26 | Programmer A |
AMUSE feasability and module selection |
| |
| |
1.2a SD module A |
2009-02-27 | 2009-06-10 | Programmer A |
AMUSE stellar dynamics module |
| |
| |
1.3 SD common interface |
2009-06-11 | 2009-07-22 | Programmer A |
AMUSE stellar dynamics common interface |
| |
| |
3.2b GD module B |
2009-07-23 | 2009-12-09 | Programmer A |
AMUSE gas dynamics module |
| |
| |
2.3 SE common interface |
2009-09-17 | 2009-10-28 | Programmer A |
AMUSE stellar evolution interface |
| |
| |
3.3 GD common interface |
2009-12-10 | 2010-01-21 | Programmer A |
AMUSE gas dynamics interface |
| |
| |
5.2 AF(SD+GD) |
2010-01-22 | 2010-02-18 | Programmer A |
SD+GD abstraction of functionality |
| |
| |
6.3 SE unit conversion class |
2010-02-19 | 2010-03-04 | Programmer A |
SE unit conversion definitions |
| |
| |
6.4 GD unit conversion class |
2010-03-05 | 2010-05-04 | Programmer A |
GD unit conversion definitions |
| |
| |
5.5 AF refactoring |
2010-03-12 | 2010-04-26 | Programmer A |
abstract functonality refactoring |
| |
| |
6.6 unit conversion refactoring |
2010-05-06 | 2010-06-02 | Programmer A |
unit conversion refactoring |
| |
| |
3.6 GD documentation |
2010-06-03 | 2010-06-09 | Programmer A |
AMUSE gas dynamics documentation |
| |
| |
4.6 RT documentation |
2010-06-10 | 2010-06-16 | Programmer A |
AMUSE radiation transfer documentation |
| |
| |
5.6 AF documentation |
2010-06-17 | 2010-06-30 | Programmer A |
documentation for abstraction of functionality |
| |
| |
2.1 SE feasability study |
2009-02-20 | 2009-02-26 | Programmer B |
AMUSE feasability and module selection |
| |
| |
1.2b SD module B |
2009-02-27 | 2009-06-10 | Programmer B |
AMUSE stellar dynamics module |
| |
| |
2.2b SE module B |
2009-06-11 | 2009-09-16 | Programmer B |
AMUSE stellar evolution module |
| |
| |
4.1 RT feasability study |
2009-09-17 | 2009-09-23 | Programmer B |
AMUSE feasability and module selection |
| |
| |
4.2a RT module A |
2009-09-24 | 2009-12-30 | Programmer B |
AMUSE radiation transfer module |
| |
| |
4.3 RT common interface |
2009-12-31 | 2010-02-11 | Programmer B |
AMUSE radiation transfer interface |
| |
| |
5.4 AF(GD+RT) |
2010-02-12 | 2010-03-11 | Programmer B |
GD+RT abstraction of functionality |
| |
| |
6.5 RT unit conversion class |
2010-03-12 | 2010-03-29 | Programmer B |
RT unit conversion definitions |
| |
| |
2.4 SE testing |
2010-03-30 | 2010-04-12 | Programmer B |
AMUSE stellar evolution testing |
| |
| |
4.4 RT testing |
2010-04-13 | 2010-04-26 | Programmer B |
AMUSE radiation transfer testing |
| |
| |
1.6 SD documentation |
2010-04-27 | 2010-05-04 | Programmer B |
AMUSE stellar dynamics documentation |
| |
| |
2.5 SE refactoring |
2010-05-06 | 2010-06-02 | Programmer B |
AMUSE stellar evolution refactoring |
| |
| |
4.5 RT refactoring |
2010-06-03 | 2010-06-30 | Programmer B |
AMUSE radiation transfer refactoring |
| |
| |
7.0 PD startup |
2009-10-29 | 2009-11-18 | Postdoc |
Start-up period for postdoctoral fellow |
| |
| |
7.1 AF(SD+SE) |
2009-11-19 | 2010-04-12 | Postdoc |
SD+SE exemplar application |
| |
| |
7.2 AF(SD+GD) |
2010-04-13 | 2010-09-01 | Postdoc |
SD+GD exemplar application |
| |
| |
7.3 AF(SE+GD) |
2010-09-02 | 2011-01-19 | Postdoc |
SE+GD exemplar application |
| |
| |
7.4 AF(GD+RT) |
2011-01-20 | 2011-06-13 | Postdoc |
GD+RT exemplar application |
| |
| |
7.5 exemplar documentation |
2011-06-14 | 2011-06-27 | Postdoc |
exemplar documentation |
| |
| |
8.1 Finalize documentation |
2011-06-28 | 2011-07-25 | Postdoc |
Finalize documentation |
| |
| |
0.0 Specify task list |
2009-01-02 | 2009-01-08 | Software engineer |
AMUSE setup global project plan |
| |
| |
0.1 Project setup |
2009-01-09 | 2009-01-15 | Software engineer |
AMUSE setup global project plan |
| |
| |
0.2 Structure design |
2009-01-16 | 2009-01-22 | Software engineer |
AMUSE genera structure design |
| |
| |
0.3 Unit testing |
2009-01-23 | 2009-01-29 | Software engineer |
AMUSE setup unit testing environment |
| |
| |
0.4 Setup documentation |
2009-01-30 | 2009-02-05 | Software engineer |
AMUSE setup documentation infrastructure |
| |
| |
0.5 Structure refactoring |
2009-02-06 | 2009-02-19 | Software engineer |
AMUSE refactor infrastructure |
| |
| |
3.1 GD feasability study |
2009-02-20 | 2009-02-26 | Software engineer |
AMUSE feasability and module selection |
| |
| |
2.2a SE module A |
2009-02-27 | 2009-06-10 | Software engineer |
AMUSE stellar evolution module |
| |
| |
3.2a GD module A |
2009-06-11 | 2009-09-16 | Software engineer |
AMUSE gas dynamics module |
| |
| |
6.2 SD unit conversion class |
2009-09-17 | 2010-03-18 | Software engineer |
SD unit conversion definitions |
| |
| |
4.2b RT module B |
2009-09-24 | 2009-12-30 | Software engineer |
AMUSE radiation transfer module |
| |
| |
5.1 AF(SD+SE) |
2009-12-31 | 2010-01-28 | Software engineer |
SD+SE abstraction of functionality |
| |
| |
5.3 AF(SE+GD) |
2010-01-29 | 2010-02-25 | Software engineer |
SE+GD abstraction of functionality |
| |
| |
6.1 Unit conversion class |
2010-02-26 | 2010-03-11 | Software engineer |
general unit conversion class definition |
| |
| |
1.4 SD testing |
2010-03-19 | 2010-04-05 | Software engineer |
AMUSE stellar dynamics testing |
| |
| |
3.4 GD testing |
2010-04-06 | 2010-04-19 | Software engineer |
AMUSE gas dynamics testing |
| |
| |
1.5 SD refactoring |
2010-04-20 | 2010-05-19 | Software engineer |
AMUSE stellar dynamics refactoring |
| |
| |
2.6 SE documentation |
2010-05-20 | 2010-05-26 | Software engineer |
AMUSE stellar evolution documentation |
| |
| |
3.5 GD refactoring |
2010-05-27 | 2010-06-23 | Software engineer |
AMUSE gas dynamics refactoring |
| |
| |
6.7 unit conversion documentation |
2010-06-24 | 2010-06-30 | Software engineer |
unit conversion documentation |
| |
| |
Start | Finish | Days | Done | Task | Dates |
2009-01-02 | 2009-01-08 | 5 | 0 | 0.0 Specify task list |
2009-01-02 - 2009-01-08, |
2009-01-09 | 2009-01-15 | 5 | 0 | 0.1 Project setup |
2009-01-09 - 2009-01-15, |
2009-01-16 | 2009-01-22 | 5 | 0 | 0.2 Structure design |
2009-01-16 - 2009-01-22, |
2009-01-23 | 2009-01-29 | 5 | 0 | 0.3 Unit testing |
2009-01-23 - 2009-01-29, |
2009-01-30 | 2009-02-05 | 5 | 0 | 0.4 Setup documentation |
2009-01-30 - 2009-02-05, |
2009-02-06 | 2009-02-19 | 10 | 0 | 0.5 Structure refactoring |
2009-02-06 - 2009-02-19, |
2009-02-20 | 2009-02-26 | 5 | 0 | 3.1 GD feasability study |
2009-02-20 - 2009-02-26, |
2009-02-27 | 2009-06-10 | 70 | 0 | 2.2a SE module A |
2009-02-27 - 2009-03-23, 2009-03-25 - 2009-04-29, 2009-05-04, 2009-05-06 - 2009-06-10, |
2009-06-11 | 2009-09-16 | 70 | 0 | 3.2a GD module A |
2009-06-11 - 2009-09-16, |
2009-09-17 | 2010-03-18 | 10 | 0 | 6.2 SD unit conversion class |
2009-09-17 - 2009-09-23, 2010-03-12 - 2010-03-18, |
2009-09-24 | 2009-12-30 | 70 | 0 | 4.2b RT module B |
2009-09-24 - 2009-12-30, |
2009-12-31 | 2010-01-28 | 20 | 0 | 5.1 AF(SD+SE) |
2009-12-31, 2010-01-04 - 2010-01-28, |
2010-01-29 | 2010-02-25 | 20 | 0 | 5.3 AF(SE+GD) |
2010-01-29 - 2010-02-25, |
2010-02-26 | 2010-03-11 | 10 | 0 | 6.1 Unit conversion class |
2010-02-26 - 2010-03-11, |
2010-03-19 | 2010-04-05 | 10 | 0 | 1.4 SD testing |
2010-03-19, 2010-03-23, 2010-03-25 - 2010-04-05, |
2010-04-06 | 2010-04-19 | 10 | 0 | 3.4 GD testing |
2010-04-06 - 2010-04-19, |
2010-04-20 | 2010-05-19 | 20 | 0 | 1.5 SD refactoring |
2010-04-20 - 2010-04-29, 2010-05-03 - 2010-05-04, 2010-05-06 - 2010-05-19, |
2010-05-20 | 2010-05-26 | 5 | 0 | 2.6 SE documentation |
2010-05-20 - 2010-05-26, |
2010-05-27 | 2010-06-23 | 20 | 0 | 3.5 GD refactoring |
2010-05-27 - 2010-06-23, |
2010-06-24 | 2010-06-30 | 5 | 0 | 6.7 unit conversion documentation |
2010-06-24 - 2010-06-30, |
Total: 380 days scheduled, 0 days completed. |
Start | Finish | Days | Done | Task | Dates |
2009-02-20 | 2009-02-26 | 5 | 0 | 1.1 SD feasability study |
2009-02-20 - 2009-02-26, |
2009-02-27 | 2009-06-10 | 70 | 0 | 1.2a SD module A |
2009-02-27 - 2009-03-23, 2009-03-25 - 2009-04-29, 2009-05-04, 2009-05-06 - 2009-06-10, |
2009-06-11 | 2009-07-22 | 30 | 0 | 1.3 SD common interface |
2009-06-11 - 2009-07-22, |
2009-07-23 | 2009-12-09 | 70 | 0 | 3.2b GD module B |
2009-07-23 - 2009-09-16, 2009-10-29 - 2009-12-09, |
2009-09-17 | 2009-10-28 | 30 | 0 | 2.3 SE common interface |
2009-09-17 - 2009-10-28, |
2009-12-10 | 2010-01-21 | 30 | 0 | 3.3 GD common interface |
2009-12-10 - 2009-12-31, 2010-01-04 - 2010-01-21, |
2010-01-22 | 2010-02-18 | 20 | 0 | 5.2 AF(SD+GD) |
2010-01-22 - 2010-02-18, |
2010-02-19 | 2010-03-04 | 10 | 0 | 6.3 SE unit conversion class |
2010-02-19 - 2010-03-04, |
2010-03-05 | 2010-05-04 | 10 | 0 | 6.4 GD unit conversion class |
2010-03-05 - 2010-03-11, 2010-04-27 - 2010-04-29, 2010-05-03 - 2010-05-04, |
2010-03-12 | 2010-04-26 | 30 | 0 | 5.5 AF refactoring |
2010-03-12 - 2010-03-19, 2010-03-23, 2010-03-25 - 2010-04-26, |
2010-05-06 | 2010-06-02 | 20 | 0 | 6.6 unit conversion refactoring |
2010-05-06 - 2010-06-02, |
2010-06-03 | 2010-06-09 | 5 | 0 | 3.6 GD documentation |
2010-06-03 - 2010-06-09, |
2010-06-10 | 2010-06-16 | 5 | 0 | 4.6 RT documentation |
2010-06-10 - 2010-06-16, |
2010-06-17 | 2010-06-30 | 10 | 0 | 5.6 AF documentation |
2010-06-17 - 2010-06-30, |
Total: 345 days scheduled, 0 days completed. |