Time Frame

Start Date:2009-01-01
Finish Date:2011-08-01

Task List

TaskStartFinishResourceDescriptionBaselineActual
1.1 SD feasability study 2009-02-202009-02-26Programmer A AMUSE feasability and module selection      
1.2a SD module A 2009-02-272009-06-10Programmer A AMUSE stellar dynamics module      
1.3 SD common interface 2009-06-112009-07-22Programmer A AMUSE stellar dynamics common interface      
3.2b GD module B 2009-07-232009-12-09Programmer A AMUSE gas dynamics module      
2.3 SE common interface 2009-09-172009-10-28Programmer A AMUSE stellar evolution interface      
3.3 GD common interface 2009-12-102010-01-21Programmer A AMUSE gas dynamics interface      
5.2 AF(SD+GD) 2010-01-222010-02-18Programmer A SD+GD abstraction of functionality      
6.3 SE unit conversion class 2010-02-192010-03-04Programmer A SE unit conversion definitions      
6.4 GD unit conversion class 2010-03-052010-05-04Programmer A GD unit conversion definitions      
5.5 AF refactoring 2010-03-122010-04-26Programmer A abstract functonality refactoring      
6.6 unit conversion refactoring 2010-05-062010-06-02Programmer A unit conversion refactoring      
3.6 GD documentation 2010-06-032010-06-09Programmer A AMUSE gas dynamics documentation      
4.6 RT documentation 2010-06-102010-06-16Programmer A AMUSE radiation transfer documentation      
5.6 AF documentation 2010-06-172010-06-30Programmer A documentation for abstraction of functionality      
2.1 SE feasability study 2009-02-202009-02-26Programmer B AMUSE feasability and module selection      
1.2b SD module B 2009-02-272009-06-10Programmer B AMUSE stellar dynamics module      
2.2b SE module B 2009-06-112009-09-16Programmer B AMUSE stellar evolution module      
4.1 RT feasability study 2009-09-172009-09-23Programmer B AMUSE feasability and module selection      
4.2a RT module A 2009-09-242009-12-30Programmer B AMUSE radiation transfer module      
4.3 RT common interface 2009-12-312010-02-11Programmer B AMUSE radiation transfer interface      
5.4 AF(GD+RT) 2010-02-122010-03-11Programmer B GD+RT abstraction of functionality      
6.5 RT unit conversion class 2010-03-122010-03-29Programmer B RT unit conversion definitions      
2.4 SE testing 2010-03-302010-04-12Programmer B AMUSE stellar evolution testing      
4.4 RT testing 2010-04-132010-04-26Programmer B AMUSE radiation transfer testing      
1.6 SD documentation 2010-04-272010-05-04Programmer B AMUSE stellar dynamics documentation      
2.5 SE refactoring 2010-05-062010-06-02Programmer B AMUSE stellar evolution refactoring      
4.5 RT refactoring 2010-06-032010-06-30Programmer B AMUSE radiation transfer refactoring      
7.0 PD startup 2009-10-292009-11-18Postdoc Start-up period for postdoctoral fellow      
7.1 AF(SD+SE) 2009-11-192010-04-12Postdoc SD+SE exemplar application      
7.2 AF(SD+GD) 2010-04-132010-09-01Postdoc SD+GD exemplar application      
7.3 AF(SE+GD) 2010-09-022011-01-19Postdoc SE+GD exemplar application      
7.4 AF(GD+RT) 2011-01-202011-06-13Postdoc GD+RT exemplar application      
7.5 exemplar documentation 2011-06-142011-06-27Postdoc exemplar documentation      
8.1 Finalize documentation 2011-06-282011-07-25Postdoc Finalize documentation      
0.0 Specify task list 2009-01-022009-01-08Software engineer AMUSE setup global project plan      
0.1 Project setup 2009-01-092009-01-15Software engineer AMUSE setup global project plan      
0.2 Structure design 2009-01-162009-01-22Software engineer AMUSE genera structure design      
0.3 Unit testing 2009-01-232009-01-29Software engineer AMUSE setup unit testing environment      
0.4 Setup documentation 2009-01-302009-02-05Software engineer AMUSE setup documentation infrastructure      
0.5 Structure refactoring 2009-02-062009-02-19Software engineer AMUSE refactor infrastructure      
3.1 GD feasability study 2009-02-202009-02-26Software engineer AMUSE feasability and module selection      
2.2a SE module A 2009-02-272009-06-10Software engineer AMUSE stellar evolution module      
3.2a GD module A 2009-06-112009-09-16Software engineer AMUSE gas dynamics module      
6.2 SD unit conversion class 2009-09-172010-03-18Software engineer SD unit conversion definitions      
4.2b RT module B 2009-09-242009-12-30Software engineer AMUSE radiation transfer module      
5.1 AF(SD+SE) 2009-12-312010-01-28Software engineer SD+SE abstraction of functionality      
5.3 AF(SE+GD) 2010-01-292010-02-25Software engineer SE+GD abstraction of functionality      
6.1 Unit conversion class 2010-02-262010-03-11Software engineer general unit conversion class definition      
1.4 SD testing 2010-03-192010-04-05Software engineer AMUSE stellar dynamics testing      
3.4 GD testing 2010-04-062010-04-19Software engineer AMUSE gas dynamics testing      
1.5 SD refactoring 2010-04-202010-05-19Software engineer AMUSE stellar dynamics refactoring      
2.6 SE documentation 2010-05-202010-05-26Software engineer AMUSE stellar evolution documentation      
3.5 GD refactoring 2010-05-272010-06-23Software engineer AMUSE gas dynamics refactoring      
6.7 unit conversion documentation 2010-06-242010-06-30Software engineer unit conversion documentation      

Milestone List

MilestoneDateBaseline
0 AMUSE Unit testing2009-02-19 
1 AMUSE stellar dynamics module2010-05-19 
2 AMUSE stellar evolution module2010-06-02 
3 AMUSE gas dynamics module2010-06-23 
4 AMUSE radiation transfer module2010-06-30 
5 AMUSE flow control layer2010-06-30 
6 AMUSE unit conversion module2010-06-30 
7 AMUSE exemplar applications2011-06-27 
8 AMUSE documentation2011-07-25 

Resources And Task Assignment

Software engineer

Start Finish Days Done TaskDates
2009-01-02 2009-01-08 5 0 0.0 Specify task list 2009-01-02 - 2009-01-08,
2009-01-09 2009-01-15 5 0 0.1 Project setup 2009-01-09 - 2009-01-15,
2009-01-16 2009-01-22 5 0 0.2 Structure design 2009-01-16 - 2009-01-22,
2009-01-23 2009-01-29 5 0 0.3 Unit testing 2009-01-23 - 2009-01-29,
2009-01-30 2009-02-05 5 0 0.4 Setup documentation 2009-01-30 - 2009-02-05,
2009-02-06 2009-02-19 10 0 0.5 Structure refactoring 2009-02-06 - 2009-02-19,
2009-02-20 2009-02-26 5 0 3.1 GD feasability study 2009-02-20 - 2009-02-26,
2009-02-27 2009-06-10 70 0 2.2a SE module A 2009-02-27 - 2009-03-23, 2009-03-25 - 2009-04-29, 2009-05-04, 2009-05-06 - 2009-06-10,
2009-06-11 2009-09-16 70 0 3.2a GD module A 2009-06-11 - 2009-09-16,
2009-09-17 2010-03-18 10 0 6.2 SD unit conversion class 2009-09-17 - 2009-09-23, 2010-03-12 - 2010-03-18,
2009-09-24 2009-12-30 70 0 4.2b RT module B 2009-09-24 - 2009-12-30,
2009-12-31 2010-01-28 20 0 5.1 AF(SD+SE) 2009-12-31, 2010-01-04 - 2010-01-28,
2010-01-29 2010-02-25 20 0 5.3 AF(SE+GD) 2010-01-29 - 2010-02-25,
2010-02-26 2010-03-11 10 0 6.1 Unit conversion class 2010-02-26 - 2010-03-11,
2010-03-19 2010-04-05 10 0 1.4 SD testing 2010-03-19, 2010-03-23, 2010-03-25 - 2010-04-05,
2010-04-06 2010-04-19 10 0 3.4 GD testing 2010-04-06 - 2010-04-19,
2010-04-20 2010-05-19 20 0 1.5 SD refactoring 2010-04-20 - 2010-04-29, 2010-05-03 - 2010-05-04, 2010-05-06 - 2010-05-19,
2010-05-20 2010-05-26 5 0 2.6 SE documentation 2010-05-20 - 2010-05-26,
2010-05-27 2010-06-23 20 0 3.5 GD refactoring 2010-05-27 - 2010-06-23,
2010-06-24 2010-06-30 5 0 6.7 unit conversion documentation 2010-06-24 - 2010-06-30,
Total: 380 days scheduled, 0 days completed.

Programmer A

Start Finish Days Done TaskDates
2009-02-20 2009-02-26 5 0 1.1 SD feasability study 2009-02-20 - 2009-02-26,
2009-02-27 2009-06-10 70 0 1.2a SD module A 2009-02-27 - 2009-03-23, 2009-03-25 - 2009-04-29, 2009-05-04, 2009-05-06 - 2009-06-10,
2009-06-11 2009-07-22 30 0 1.3 SD common interface 2009-06-11 - 2009-07-22,
2009-07-23 2009-12-09 70 0 3.2b GD module B 2009-07-23 - 2009-09-16, 2009-10-29 - 2009-12-09,
2009-09-17 2009-10-28 30 0 2.3 SE common interface 2009-09-17 - 2009-10-28,
2009-12-10 2010-01-21 30 0 3.3 GD common interface 2009-12-10 - 2009-12-31, 2010-01-04 - 2010-01-21,
2010-01-22 2010-02-18 20 0 5.2 AF(SD+GD) 2010-01-22 - 2010-02-18,
2010-02-19 2010-03-04 10 0 6.3 SE unit conversion class 2010-02-19 - 2010-03-04,
2010-03-05 2010-05-04 10 0 6.4 GD unit conversion class 2010-03-05 - 2010-03-11, 2010-04-27 - 2010-04-29, 2010-05-03 - 2010-05-04,
2010-03-12 2010-04-26 30 0 5.5 AF refactoring 2010-03-12 - 2010-03-19, 2010-03-23, 2010-03-25 - 2010-04-26,
2010-05-06 2010-06-02 20 0 6.6 unit conversion refactoring 2010-05-06 - 2010-06-02,
2010-06-03 2010-06-09 5 0 3.6 GD documentation 2010-06-03 - 2010-06-09,
2010-06-10 2010-06-16 5 0 4.6 RT documentation 2010-06-10 - 2010-06-16,
2010-06-17 2010-06-30 10 0 5.6 AF documentation 2010-06-17 - 2010-06-30,
Total: 345 days scheduled, 0 days completed.

Programmer B

Start Finish Days Done TaskDates
2009-02-20 2009-02-26 5 0 2.1 SE feasability study 2009-02-20 - 2009-02-26,
2009-02-27 2009-06-10 70 0 1.2b SD module B 2009-02-27 - 2009-03-23, 2009-03-25 - 2009-04-29, 2009-05-04, 2009-05-06 - 2009-06-10,
2009-06-11 2009-09-16 70 0 2.2b SE module B 2009-06-11 - 2009-09-16,
2009-09-17 2009-09-23 5 0 4.1 RT feasability study 2009-09-17 - 2009-09-23,
2009-09-24 2009-12-30 70 0 4.2a RT module A 2009-09-24 - 2009-12-30,
2009-12-31 2010-02-11 30 0 4.3 RT common interface 2009-12-31, 2010-01-04 - 2010-02-11,
2010-02-12 2010-03-11 20 0 5.4 AF(GD+RT) 2010-02-12 - 2010-03-11,
2010-03-12 2010-03-29 10 0 6.5 RT unit conversion class 2010-03-12 - 2010-03-19, 2010-03-23, 2010-03-25 - 2010-03-29,
2010-03-30 2010-04-12 10 0 2.4 SE testing 2010-03-30 - 2010-04-12,
2010-04-13 2010-04-26 10 0 4.4 RT testing 2010-04-13 - 2010-04-26,
2010-04-27 2010-05-04 5 0 1.6 SD documentation 2010-04-27 - 2010-04-29, 2010-05-03 - 2010-05-04,
2010-05-06 2010-06-02 20 0 2.5 SE refactoring 2010-05-06 - 2010-06-02,
2010-06-03 2010-06-30 20 0 4.5 RT refactoring 2010-06-03 - 2010-06-30,
Total: 345 days scheduled, 0 days completed.

Postdoc

Start Finish Days Done TaskDates
2009-10-29 2009-11-18 15 0 7.0 PD startup 2009-10-29 - 2009-11-18,
2009-11-19 2010-04-12 100 0 7.1 AF(SD+SE) 2009-11-19 - 2009-12-31, 2010-01-04 - 2010-03-19, 2010-03-23, 2010-03-25 - 2010-04-12,
2010-04-13 2010-09-01 100 0 7.2 AF(SD+GD) 2010-04-13 - 2010-04-29, 2010-05-03 - 2010-05-04, 2010-05-06 - 2010-09-01,
2010-09-02 2011-01-19 100 0 7.3 AF(SE+GD) 2010-09-02 - 2011-01-19,
2011-01-20 2011-06-13 100 0 7.4 AF(GD+RT) 2011-01-20 - 2011-03-18, 2011-03-22 - 2011-03-23, 2011-03-25 - 2011-05-04, 2011-05-06 - 2011-06-13,
2011-06-14 2011-06-27 10 0 7.5 exemplar documentation 2011-06-14 - 2011-06-27,
2011-06-28 2011-07-25 20 0 8.1 Finalize documentation 2011-06-28 - 2011-07-25,
Total: 445 days scheduled, 0 days completed.